Recently, we’ve received many inquiries from clients in manufacturing, real estate, and energy:
“When starting a project in the Philippines, do we need an ECC? How do we apply? Is it complicated?”
Today, we’ll explain the Philippine Environmental Compliance Certificate (ECC) in the clearest terms: what it is, who needs it, how to apply, and what to watch out for after obtaining it.
01
What is an ECC and why must you obtain it before starting construction?
The ECC is a “permit to develop” issued by the Environmental Management Bureau (EMB) under the Department of Environment and Natural Resources (DENR). It certifies that your project has been reviewed and is unlikely to cause unacceptable environmental impacts, allowing construction to proceed.
The legal basis is Presidential Decree No. 1586, making it a mandatory permit. In general, any project involving construction + land development + emissions/resource use must go through this process.
Examples of projects requiring an ECC in the Philippines:
Large-scale infrastructure: bridges, highways, airports, ports
Industrial facilities: power plants, factories, refineries
Mining operations: exploration, development, extraction of minerals or natural resources
Agri-industrial projects: large-scale commercial farms, fish ponds, feedlots
Tourism and recreational facilities: theme parks, golf courses, beach resorts
Logging and commercial tree plantations
Development projects: residential subdivisions, commercial complexes, industrial parks
Even ordinary projects located in environmentally sensitive areas—riversides, hillsides, coastlines—must be declared. If construction begins without an ECC, the project can be halted, fined, or blacklisted by EMB, affecting future operations.
📌 Case example:
Last year, an oil palm project on Negros Island began clearing forest land without an ECC. It was exposed by media, DENR intervened, and construction was stopped and restored.
02
How to Apply for an ECC in the Philippines
The EMB now has an online ECC application system, allowing some documents to be submitted digitally. The overall process is as follows:
Determine project type: Assess whether it is an ECP (Environmentally Critical Project) or located in an ECA (Environmentally Critical Area), based on DENR AO 2003-30.
Prepare environmental reports:
Standard projects submit an Initial Environmental Examination (IEE)
ECPs (large-scale or high-risk) submit a full Environmental Impact Statement (EIS)
Public consultation: Some projects require hearings or community feedback, especially those near villages, coastlines, or forest areas. Community input is incorporated into the EIA report.
Submit documents and pay fees: Prepare and submit all required documents and complete the payment. (Document checklist image)
EMB review and site evaluation: Regional office reviews documents, conducts site inspections, and submits an evaluation report.
ECC issuance: If conditions are met and approved, the ECC is issued. Usually valid for 5 years. If the project is delayed for a long time, the ECC expires and must be re-applied.
03
What to watch out for after obtaining an ECC
Getting an ECC is just the first step—compliance is ongoing:
Submit a Compliance Monitoring Report (CMR) every six months to EMB;
Assign personnel responsible for environmental management;
Report any project design changes, relocation, or expansion for approval;
EMB can conduct random inspections or respond to third-party complaints.
Case example:
A processing plant that expanded without updating its ECC was ordered to stop operations by the local environmental office and had to reapply before resuming.
To ensure smooth project implementation and compliance:
Assess ECC requirements early during land acquisition or project design; avoid protected areas, wetlands, or indigenous settlements if possible;
Prepare professional documentation, with IEEs/EISs drafted by experienced local consultants;
Engage with local communities and government via hearings;
Establish compliance mechanisms immediately after obtaining the ECC, including monitoring and reporting.
In short, when setting up projects in the Philippines, policy changes, environmental scrutiny, and community involvement cannot be ignored. For formal enterprises, the ECC should be treated as a pre-construction priority—not only affecting approval speed but also your ability to construct, attract investors, secure financing, and ultimately complete and operate the project successfully.